From: Jorge Campo <Jorge.Campo@rne.eu>
Sent: Wednesday, September 26, 2018 08:15
To: Gorazd Titizov
Cc: Máté Bak; i=rne-014-9
Subject: RE: New EC test release
Hi again,
Perhaps you can just tell us if the notes created by Máté (included also below) are correct:
https://cms.rne.eu/pcs-eec-project/discussions/pcs-ec-sprint-13-be-checked-26th-september
Thanks!
Jorge
PCS EC Sprint 13 to be checked on 26th September
By
Máté Bak on Thursday, September 20 - 15:30pm
Sprint is scheduled until 24th September. Deploy on PCS Test 3 is expected on 24th or 25th September.
Added features
Path variants
- A read-only view is implemented for the geography of the path variant
Alternative origin/destinations
- Editing of sub-path in the first territory should show an option in the last path section for marking an alt. destination.
- Editing of sub-path in mid territory should show an option in the first path section for marking alternative origin and in the last path section for marking an alt. destination.
- Editing of sub-path in the last territory should show an option in the first path section for marking an alt. origin.
- Intermediate points of a sub-path cannot be marked as alternative origin/destination
- Origin point of a sub-path in the first territory cannot be marked as an alternative origin
- Destination point of a sub-path in the last territory cannot be marked as an alternative destination
Acceptance indicator downgrades
- Because of a calendar change
- Because of changes on the border (time, dwell time, operation point, alternative origin/destination)
- Downgrade procedure of the acceptance indicators:
- Neighbour RU light should go from green to yellow when my
- Border location is changed
- Calendar is changed
- Time on the border is changed
- Neighbour IM light should go from green to yellow in the same cases, but only when I set green light
- Neighbour RU light should go from green to yellow when my
Basic Data
- Edit basic data
- Edit dossier-level parameters
- Change of leading agency
- Change acceptance indicator for production and service agencies
Not available features (without a complete enumeration)
Access Control is not implemented yet
Dossier header is hardcoded that is why you see always "262/2018/Öbb Rome 6.3"
Following dossier segments are not in place yet:
- Train information
- Train composition
- Connections
- Links
- Composite relations
- Attachments
- History
Previous/Next button in the navigation among the dossiers
Links for edit parameter in the Control
From: Jorge Campo
Sent: 26 September, 2018 07:56
To: 'Gorazd Titizov' <Gorazd.Titizov@netcetera.com>
Cc: Máté Bak <mate.bak@rne.eu>; i=rne-014-9 <i=rne-014-9@mailstore.netcetera.com>
Subject: RE: New EC test release
Hi Gorazd,
Thank you very much to you and the team for the release.
Do you have the release notes or some notes of the changes?
Best,
Jorge
From: Gorazd Titizov <Gorazd.Titizov@netcetera.com>
Sent: 25 September, 2018 19:23
To: Jorge Campo <Jorge.Campo@rne.eu>
Cc: Máté Bak <Mate.Bak@rne.eu>; i=rne-014-9 <i=rne-014-9@mailstore.netcetera.com>
Subject: Re: New EC test release
Hi Jorge,
A new version of EC was deployed on test3.
Best regards and have a nice evening,
Gorazd
--
Living proof of 20 years of software ingenuity: http://netcetera.com/20years
Gorazd Titizov | gorazd.titizov@netcetera.com | T +389 2 306 45 32 |
Netcetera DOOEL | 1000 Skopje | Macedonia | http://netcetera.com |
On Sep 25, 2018, at 12:46, Gorazd Titizov <Gorazd.Titizov@netcetera.com> wrote:
Hi Jorge,
Yes, a new release on test3 will be deployed by end of day latest.
I will write to you when it's done.
Best regards,
Gorazd
--
We innovate. You win. http://netcetera.com
Gorazd Titizov | gorazd.titizov@netcetera.com | T +389 2 306 45 32 |
Netcetera DOOEL | 1000 Skopje | Macedonia | http://netcetera.com |
From: Jorge Campo <Jorge.Campo@rne.eu>
Sent: Tuesday, September 25, 2018 10:57
To: Gorazd Titizov
Cc: Máté Bak
Subject: New EC test release
Hi Gorazd,
If I understood properly you must have ready a new EC version today at https://pcstest3.rne.eu/pcs/#/login so I can test it today.
Do you have any news?
I see the 10th of September version in the main page.
Jorge Campo
JO PCS Functional Manager
RailNetEurope
Oelzeltgasse 3/8
1030 Vienna
Austria
Phone: +43 (0) 1 907 62 72 19
Fax: +43 (0) 1 907 62 72 90
Mobile: +43 (0) 664 884 248 09
E-Mail: jorge.campo@rne.eu
Web: www.rne.eu
Please consider the environment before printing this e-mail!
This message and any files transmitted with it contain confidential information. It is intended only for the use of the person(s)
named above and, unless otherwise specifically stated, may not be used for any other purpose than that for which it was made
available or disclosed by the sender. If you have received this e-mail in error, please let us know by replying to the sender, and
immediately delete the e-mail from your system. RailNetEurope does not accept any liability for the contents of this message.
Unless specifically stated otherwise, no rights can be derived from this email.
Hi Jorge,
Regarding the sprint:
- Acceptance indicators downgrade - yes, available, all of it.
- Basic data (read and edit mode) - yes, available.
-- Dossier Information
-- Participating agencies
-- Special agreement, IM details
- Basic data: Editing parameters - not fully available, will be after current sprint.
- Basic data: Change acceptance indicator for production and service agencies - not available yet (current sprint)
- Basic data: Change of leading agency - not available yet (current sprint)
- Path variants - in general the path variants view is implemented fully, it can be checked out. The path variants editing is being done in the current sprint.
-- geography path variant view - done,
-- calendar path variant view - done,
-- weekly calendar path variant views - done
Just, again, all of this is work in progress, the features listed are finished and tested by the devs and Jana/Valerija, but not in a thorough manner. It's like a building that is being built. The rooms/wiring are done, but it needs cleaning, polishing etc. It can be checked out, but it's not fit for moving in yet.
Best regards,
Gorazd
--
We innovate. You win. http://netcetera.com
Gorazd Titizov | gorazd.titizov@netcetera.com | T +389 2 306 45 32 |
Netcetera DOOEL | 1000 Skopje | Macedonia | http://netcetera.com |