Period: Submission of Late Path Requests 2020
15/04/2020, at 00:01: All dossiers submitted after this deadline will be treated by the IMs/ABs as late path requests. The system checks regularly (every night) the status of acceptance indicators of the dossiers and automatically transfers those dossiers where all applicants’ lights are green at 23:00 h to late path request until 19/10/2020.
This is the second process for placing path requests into the regular yearly timetable. The date when a dossier is opened determines what kind of path request is made. The new dossier with process type Late Path Request will be made when it is opened after X-8 until X-2. The X means the date when the new yearly timetable starts. The numbers mean months before the date X. Dossiers in this process should be submitted as Late Path Request until X-2. Dossier opened after X-8 until X-2, but submitted as a request after X-2 is automatically changed into the corresponding process type Ad hoc Path Request.
The whole process consists of the following phases:
Open – Applicant phase
Harmonization – Applicant phase
Path Request – IM phase
Path Elaboration – IM phase
Late Request Offer – Milestone
Acceptance – Applicant phase
Post-processing – IM phase (optional)
Final Offer – Applicant phase (optional)
Active timetable – Final phase
Closed – Archived phase
All the process steps for Late Path Request are the same as for New Path Request. The milestone “Draft Timetable” has the name “Late Request Offer” and the step “Observations” has the name “Acceptance”. However, if Applicants put all acceptance indicators (traffic lights in the control panel) to green already in “Acceptance” (actually, during the observations), the system will understand that the draft offer of IMs is suitable for all Applicants and switch automatically the dossier into the “Active Timetable” phase at the midnight on the same day when the last Applicant has put the green indicator. This is done in order to get through the path request process faster. The system prevents IMs to give a Late Request Offer until the deadline for Final Offers for regular Path Requests is passed.
The dossier should run through the process steps until the Active timetable and it should be closed when it is not needed anymore. Further information about process steps could be found under the description of phases.
Overview of Late Path Request
From X-8 until X-2 (for further dates please check PCS Process Guidelines)
Late path requests for the next annual timetable
- First day for submission of Late path requests: 2022-04-12
- First day for answers to Late path requests: 2022-08-23
- Last day for submission of Late path requests for timetable 2022 (X-2): 2022-10-17
- Last day for answers to Late path requests: 2022-11-16