Milestone: Limit for answering path study requests
When:
Monday, Mar 13, 2023,
23:59
Where:
Mar
13
13/03/2023 at 23.59 (the limit for answering path study requests): Automatically switching all dossiers which are in Feasibility Elaboration Conference to Harmonization – IMs/ABs lights may be green, yellow, red, or blue (IMPORTANT: the Feasibility Study Result will be treated in the system as ‘acknowledged’).
In case when the feasibility study CAN NOT be completed by the IM/AB on time, and they decide that this dossier should NOT be switched automatically to Harmonisation on 13.03.2023 at 23.00 h. then the IM/AB has to switch this dossier manually from Feasibility Elaboration Conference to Feasibility Study Elaboration before 13.03.2023 at 23.00 h.