Milestone: Limit for answering path study requests
14/03/2022 at 23.59 (the limit for answering path study requests): Automatically switching all dossiers which are in Feasibility Elaboration Conference to Harmonization – IMs/ABs lights may be green, yellow, red, or blue (IMPORTANT: the Feasibility Study Result will be treated in the system as ‘acknowledged’).
In case a feasibility study cannot be completed by the IM/AB in due time, and the dossier should not yet automatically be switched to Harmonisation on 14/03/2022 at 23.59 h, the IM/AB has to switch this dossier manually from Feasibility Elaboration Conference to Feasibility Study Elaboration before 14/03/2022 at 23.59 h. Afterward, the switching from Feasibility Study Elaboration to Feasibility Study Result has to be done manually by the coordinating IM/AB.