Other

Period: Preparation Final Offer

Submitted by Anna Géczi on 31 October, 2022 - 14:16

Between 05/08/2023 and 21/08/2023, IMs/ABs/RFCs prepare the final answers to the customers.

In this phase, IMs/ABs/RFCs may optimize the train path. Once all IMs/ABs/RFCs have finished their final adjustments, the dossier is moved to the Final Offer phase. 

From 05/08/2023 till 09/12/2023 at 03:00, the system checks the status of acceptance indicators of the dossiers and transfers those dossiers that have all IMs/ABs/RFCs light on green automatically to the Final Offer phase.

Deadline: Draft Offer

Submitted by Anna Géczi on 31 October, 2022 - 14:03

03/07/2023, at 03:00 and 23.00: All agreed and harmonized dossiers with all green lights will be switched automatically from Path Elaboration via Draft Timetable to Observations. After this deadline, the coordinating IM/AB/RFC may switch dossiers with all green lights manually. All Applicant's lights changes to blue in Observations.

 

RNE Technical Meeting

Submitted by Anna Géczi on 31 October, 2022 - 14:00

By 12/06/2023: In order to fulfil the harmonization process during the RNE Technical Meeting, all IMs/ABs have to ensure the availability of the constructed/designed train path. RNE Technical meeting will be held from 12th to 16th June 2023.